How to install Rollmate, add roll-up fields, choose which work items count, and keep the values right.

On this page

What Rollmate doesLink to this section

Rollmate adds read-only fields to parent work items, such as epics, and keeps them up to date from the work items underneath. Each roll-up is a real Jira custom field, so it works in JQL, filters, boards, dashboards and exports.

  • When a child work item is created, changed, moved or deleted, the parent’s fields update within seconds.
  • When someone logs work, time-based fields update too.
  • Dates and overdue counts are also refreshed once a day, because time passing doesn’t trigger a change.
  • Rollmate uses no Jira Automation rules and runs entirely on Atlassian’s cloud.

Example: an epic has four stories with 8, 5, 3 and 2 story points, and the 8-point story is Done. The epic shows Total story points 18, Remaining story points 10 and Progress (by story points) 44%.

your-site.atlassian.net/browse/SHOP-12
Shop / SHOP-12
Checkout redesign
Child work items
SHOP-14Single-page checkout form8In Progress
SHOP-15Save card for next purchase5Done
SHOP-16Show order summary before paying3Done
SHOP-17Coupon code ignored on mobile Safari2To Do
Rollmate
8 of 18 story points done44%
Needs attention
1Overdue work items: SHOP-14
1Open bugs: SHOP-17
To Do
In Progress
Done
SHOP-12 has four child work items. When SHOP-14 moves to Done, the epic’s Rollmate fields and panel update within seconds.

Install RollmateLink to this section

Rollmate isn’t on the Atlassian Marketplace yet

These steps will be available once Rollmate is listed. They describe how installing will work.

You need to be a Jira administrator, or have permission to install apps, on a Jira Cloud site.

  1. In Jira, open Apps and choose Explore more apps.
  2. Search for Rollmate and open the app.
  3. Start a free trial or buy it. Billing goes through your Atlassian account, like other Marketplace apps.
  4. Review the permissions on the consent screen and accept. Each one is explained below.

Sites with up to 10 users can use Rollmate for free. See pricing.

Check the permissions it asks forLink to this section

When you install Rollmate, Jira shows a list of what the app may do. Here is what Rollmate uses each permission for.

PermissionWhat Rollmate uses it for
read:jira-work
View Jira work item data
Read child work items (story points, status, dates, time) to calculate values. List projects, fields and work item types for setup. Receive events when work items change.
read:jira-user
View user information
Show the names of admins in the change history. Names are looked up when shown, not stored.
write:app-data:jira
Write app data in Jira
Write calculated values into Rollmate's own read-only fields. It can't write to any other field.
storage:app
Store app data
Save field settings, change history and health counters in Atlassian's Forge storage.
manage:jira-project
Manage project settings
Only for Add field to screens: put Rollmate's fields on project screens, and check whether a field is on any screen for the Health tab.
manage:jira-configuration
Manage Jira global settings
Only to read which screens each company-managed project uses, so Add field to screens knows where to put the field.

Why does the app ask to manage project and Jira settings?

Only so Add field to screens can place Rollmate’s fields on your company-managed projects’ screens for you. Rollmate never changes workflows, permissions or other settings. Prefer to do it yourself? Skip the button and add the fields to screens in Jira.

Open the Rollmate admin pageLink to this section

  1. In Jira, select Settings (the cog), then Apps.
  2. In the sidebar, choose Rollmate.

Only Jira administrators can open the Rollmate admin page and change settings. It has three tabs: Fields, Health and Settings.

The top of the Fields tab shows Active fields, Values updated in the last 7 days, Automation steps saved (roughly how many Jira Automation steps the same roll-ups would have used; Rollmate uses none) and a Health summary that opens the Health tab. How it works opens a short explanation.

Add your first fieldLink to this section

Adding a field takes three steps: Choose, Configure and Preview.

  1. On the Fields tab, select Add field. If you have no fields yet, select Browse templates. You can also pick a template straight from Add from a template under your fields.
  2. Choose. Pick a template. Use the category buttons (All, Numbers, Progress, Time, Dates, Risk, People) to narrow the list, or pick Start from scratch to choose the field and calculation yourself.
  3. Configure. Check the Field name (shown on work items and in JQL), for example “Total story points”. Adjust what it reads and how values combine (see Choose what the field reads). The In plain words box describes what the field will do. Select Preview.
  4. Preview. Pick a real work item, such as an epic, and see the value it would get, child by child, with whether each child was counted. Nothing is written to Jira.
  5. Leave Add the field to company-managed project screens and Fill in existing work items now ticked, then select Create field.

Rollmate confirms with “Created” and the field name, and starts filling in existing work items in the background. A new field usually takes up to a minute to appear in Jira. A banner shows progress until it says Existing work items are up to date.

your-site.atlassian.net/jira/settings/apps
Rollmate
Add a field
Pick what you want to see on parent work items. You can fine-tune it on the next step.
AllNumbersProgressTimeDatesRiskPeople
Total story pointsNumbers
Adds up the story points of all child work items.
18
Number of work itemsNumbers
Counts the child work items.
12
Progress (by story points)Progress
Share of story points in Done.
▰▰▰▰▰▰▱▱▱▱ 60%
Progress (by work items)Progress
Share of child work items in Done.
▰▰▰▰▱▱▱▱▱▱ 40%
Remaining story pointsProgress
Story points not yet Done.
7
Time spent vs estimateTime
Logged time as a share of the original estimate.
▰▰▰▰▰▰▰▰▱▱ 80%
Field name (shown on work items and in JQL)Total story points
Read this field from each childStory point estimate
Combine the values by
Adding them up (sum)Average
In plain words
Sum of Story point estimate from direct children
On SHOP-12 · Checkout redesign
18
Work itemSummaryValueCounted?
SHOP-14Single-page checkout form8Counted
SHOP-15Save card for next purchase5Counted
SHOP-16Show order summary before paying3Counted
SHOP-17Coupon code ignored on mobile Safari2Counted
BackPreview
FieldsHealthSettings
Filling in existing work itemsDismiss
0 of ~18 work items checked
Fields
Add field
Total story pointsNumbers
Sum of Story point estimate from direct children
Last updated just now
Add from a template
Browse all templates
Number of work itemsNumbers
Progress (by story points)Progress
Progress (by work items)Progress
Choose, Configure, Preview, then Create field. The banner shows existing work items being filled in.

Templates you can start fromLink to this section

Fifteen templates in six groups. The example shows the kind of value each field holds.

TemplateWhat it showsExample
Total story points
Numbers
Adds up the story points of all child work items.18
Number of work items
Numbers
Counts the child work items.12
Progress (by story points)
Progress
Share of story points in Done.60%
Progress (by work items)
Progress
Share of child work items in Done.40%
Remaining story points
Progress
Story points not yet Done.7
Time spent vs estimate
Time
Logged time as a share of the original estimate. Over 100% means over budget. Counts every level below.80%
Remaining estimate (hours)
Time
Hours still estimated across all work below. Counts every level below.34.5
Latest due date
Dates
When the last child is due: the realistic finish date.15/Dec/26
Earliest start date
Dates
When the first child starts.02/Nov/26
Overdue work items
Risk
Children past their due date and not Done.2
Due after parent
Risk
Children due later than the parent itself: the plan will slip.1
Open bugs
Risk
Bugs underneath that are not Done. Counts every level below.3
Flagged work items
Risk
Children flagged as impeded.1
Unestimated work items
Risk
Children without story points: the total may be too low.4
Contributors
People
Everyone assigned to work below the parent. Counts every level below.3 people

Templates that use story points or a start date find the right field on your site. If a template needs a story point field your site doesn’t have, its card says so and you can pick another field on the next step. If your site has two story point fields, Rollmate shows Two story point fields found on the Configure step, so you can pick the one your teams use.

Choose what the field readsLink to this section

On the Configure step you decide what the field reads and how it combines values. The options depend on the kind of field.

KindOptions
NumbersRead this field from each child: any number field, such as a story point field or Original estimate. Combine the values by: Adding them up (sum), Average, Lowest, Highest, or Counting the work items.
ProgressMeasure progress by a number field (such as story points) or by Number of work items (each counts as 1). Show: % complete (progress bar), Amount Done, or Amount remaining. Done means the work item’s status is in the Done category.
TimeShow: Time spent as % of estimate (progress bar), Hours logged, Hours remaining, or Hours originally estimated.
DatesRead this date from each child: Due date or another date field, such as Start date. Show the Latest date (when everything finishes) or Earliest date (when work starts).
RiskCount the children that are: Overdue (past due date and not Done), Due after the parent’s own due date, Open bugs, Flagged, or Without story points.
PeopleCollect everyone in Assignee, Reporter or another user field.

If no child has a value, the field is left empty rather than set to 0.

Choose which work items countLink to this section

Open Advanced options on the Configure step to limit what the field counts.

Which work items count
Direct children only (stories under an epic), or Every level below (stories and their sub-tasks). Time, Open bugs and Contributors templates start with every level below.
Projects
All projects, or only the projects you pick.
Only these work item types
For example only Story and Bug. Leave it empty for all types.
Only children in these statuses
To Do, In Progress, Done. Leave all unticked for any status. Progress fields and the Overdue count don’t show this option, because they decide by status themselves.
Also add the parent’s own value
For number and time fields: include the parent’s own value in the result.

Changing a field later

Saving changes recalculates the field for all parents. Existing work items are filled in again right after you save.

Show the fields on work itemsLink to this section

Company-managed projectsLink to this section

A field only shows in work item details if it’s on the project’s screens. Rollmate can do this for you: tick Add the field to company-managed project screens when you create the field, or later choose Add field to screens from the field’s menu. Rollmate adds it to the screens your projects use and tells you how many screens it added it to.

You can also add it yourself in Jira’s screen settings, like any custom field.

Team-managed projectsLink to this section

Team-managed projects don’t use screens, so Add field to screens can’t place the field. A project admin adds it in the project’s settings, in the field layout for each work item type.

Fields work in search, filters and the Rollmate panel whether or not they’re on a screen or layout.

Use the fields in search, boards and dashboardsLink to this section

Each roll-up is a Jira custom field named whatever you called it when you added it. Use that name in JQL, in quotes. This works even if the field isn’t on any screen.

your-site.atlassian.net/jira/settings/apps
Rollmate
FieldsHealthSettings
Active fields
11 of 11
Values updated
99
Automation steps saved
495
Health
Healthy
Fields
How it worksAdd field
Total story pointsNumbers
Sum of Story point estimate from direct children
Last updated 3 h ago
Remaining story pointsProgress
Story point estimate not yet Done from direct children
Last updated 3 h ago
Progress (by story points)Progress
% of Story point estimate that are Done from direct children
Last updated 3 h ago
Latest due dateDates
Latest Due date from direct children
Last updated 3 h ago
Overdue work itemsRisk
Number of work items past their due date and not Done from direct children
Last updated 3 h ago
Roughly how many Jira Automation steps the same roll-ups would have used in the last 7 days. Rollmate uses none.
The Fields tab lists every roll-up field. The same fields work in a Jira search.
"Total story points" > 20 AND "Overdue work items" > 0
issuetype = Epic AND "Progress (by story points)" < 50
ORDER BY "Latest due date" ASC
issuetype = Epic AND "Unestimated work items" > 0
  • Filters: save a search like the ones above as a filter, and share it.
  • Boards: use the field in board filters and quick filters, or show it on cards where your board settings allow it.
  • Dashboards: show it through filter-based gadgets, such as a filter results gadget with the field as a column.
  • Exports: include it in CSV exports, like any other field.

Check a value on a work itemLink to this section

Open a work item that has children and open the Rollmate panel from the work item’s apps. It shows every roll-up for that work item, calculated live:

  • Progress, for example “8 of 18 story points done”, with a progress bar.
  • Needs attention: any risk count above zero, with the keys of the work items behind it.
  • Other values, such as dates, totals and contributors.

Show breakdown opens How it’s calculated: pick a field to see each child, its value and whether it was counted. Refresh reloads the panel. If a stored value is behind, the panel shows Update now to recalculate that work item.

The panel reads work items as the person viewing it, so its breakdown only lists children they can see.

Manage your fieldsLink to this section

The Fields tab lists each roll-up field with its category and when it was last updated. Each field has an on/off switch and an actions menu:

Edit
Change what it adds up and which work items count.
Preview on a work item
Pick an epic and see the value it gets, child by child. Calculated live from Jira; nothing is written.
Refresh all values
Recalculate this field on every work item now.
Add field to screens
Show the field in work item details in company-managed projects.
Compare with another field
Check its values against a field you already keep, for example one set by Automation.
Delete
Remove the field from Jira. See below.

Turn a field off or delete itLink to this section

  • Turn off with the switch to stop updates without deleting anything. The field keeps its last values until you turn it back on. Turning it on fills in existing work items again.
  • Delete from the actions menu, then Delete field. The field stops updating and is removed from Jira, including from screens, filters and board cards that use it. Adding it again later creates a new field and fills it in from scratch.

If you might want the field back, turn it off instead of deleting it.

Refresh all valuesLink to this section

Values update on their own when work items change. Use Refresh all values from a field’s menu if a value looks wrong, or after a change Jira doesn’t send an event for. Every work item with that field is recalculated in the background, and a banner shows progress:

  • Finding work items to update…, then Filling in existing work items with a count of work items checked.
  • Paused: Jira asked us to slow down. It will continue automatically. On large sites Jira may limit how fast apps can work. You don’t need to do anything.
  • Existing work items are up to date when it’s finished.

You can leave the page while this runs.

Compare with a field you already keepLink to this section

If you already keep a total in another field, for example one set by an Automation rule, check that the two agree before you switch.

  1. From the roll-up field’s menu, choose Compare with another field.
  2. Pick the field you keep today. The comparison runs straight away. Nothing is changed in Jira.

The result says Both fields agree, or lists the work items where they don’t, marked Different value or Empty in other field. Open a couple of them to see which total is right before you turn anything off. Compare again runs it again.

Fix problems on the Health tabLink to this section

The Health tab checks your setup and shows Recalculations, Values updated, Automation steps saved and Failed updates over the last 7 days. Each check is marked Problem, Check or OK. Where Rollmate can fix something, there’s a button. When everything is fine you’ll see Everything looks good.

CheckWhat it meansFix
“Field name” is missing from JiraIts Jira field was removed, so values have nowhere to go.Create it again
“Field name” field is still being createdJira usually lists new fields within a minute.Wait a minute
“Field name” reads a field that no longer existsA field it reads from was deleted.Edit the field and pick another one
“Field name” isn’t on any screenIt works in search, filters and the Rollmate panel, but people won’t see it in work item details yet.Add to screens
“Field name” is turned offIts field keeps the last calculated values until you turn it back on.Turn it back on
Duplicate fieldsTwo or more fields are calculated the same way.Remove duplicates
Two story point fieldsYour site has more than one story point field. Make sure each field reads the one your teams use.Edit the field
Updates failed this weekSome updates failed. Failed updates are retried automatically. The most recent error is shown.Usually none needed
Existing work items not filled in yetValues appear as soon as something changes, or you can fill in everything now.Fill in now
Close to the field limitA site can have up to 100 Rollmate fields.Delete fields you don’t use

Copy fields to another siteLink to this section

Copy your roll-up fields from one Jira site to another, for example from a sandbox to production.

  1. On the source site, open the Settings tab. Under Move fields between sites, select Export and save the file.
  2. On the target site, open Settings, select Import, then Choose file or paste the file’s contents, and select Import.

The export holds field settings only, not values. Fields that already exist on the target site are skipped. Imported fields are filled in on the new site from its own data. If a field one of them reads doesn’t exist on the new site, the Health tab tells you, so you can pick another one.

See who changed whatLink to this section

The Settings tab also shows the Change history: when, who, what (Created, Edited, Turned on, Turned off, Deleted, Imported, Filled in), which field, and details. It keeps the last 200 changes.

Pricing, and what happens if the subscription lapsesLink to this section

Rollmate is free for sites with up to 10 users. Larger sites pay US$0.50 per user per month, billed through the Atlassian Marketplace. See pricing.

If the site’s subscription isn’t active, Rollmate pauses:

  • The admin page shows Rollmate is paused: “Your Rollmate subscription isn’t active. A Jira admin can renew it in Manage apps.”
  • The Rollmate panel says Rollmate isn’t active on this site, so roll-ups aren’t updating.
  • Your fields and settings are kept. Roll-ups start updating again once the subscription is active.

LimitsLink to this section

  • Up to 100 Rollmate fields per Jira site. This is a Forge platform limit.
  • Values usually update within seconds of a change. On busy sites, or right after a bulk change, it can take longer.
  • Jira Cloud only. There’s no Data Center version.
  • Roll-up fields are read-only. You can’t type a value into them.

Uninstall RollmateLink to this section

To remove a single field, use Delete from its menu. The Jira field is removed.

To remove the app, go to Settings › Apps › Manage apps, find Rollmate and choose Uninstall. Then:

  • Roll-up fields and their values disappear from Jira. Jira keeps app field data for 30 days in case the app is reinstalled, then deletes it.
  • Field settings, change history and health counters in Atlassian-hosted storage are deleted by Atlassian after its retention period.
  • Rollmate keeps no copy of your data anywhere else.

Before uninstalling, update any filters, boards or dashboards that use roll-up fields. More detail is in the privacy policy.

TroubleshootingLink to this section

I can’t see the field on a work item.

It’s probably not on the project’s screens. Open the Health tab, or choose Add field to screens from the field’s menu. In team-managed projects, add it to the work item layout yourself. You can always check values in the Rollmate panel.

The value looks wrong.

Use Preview on a work item on that parent to see which children were counted and why. Check the field’s Advanced options: which work items count, projects, work item types and statuses. If your site has two story point fields, make sure the field reads the one your teams use.

The field is empty on older work items.

Existing work items may not be filled in yet. Choose Refresh all values, or Fill in now on the Health tab. A field is also left empty when no child has a value to add up.

A value didn’t change after an edit.

Updates usually take a few seconds. Jira’s search can lag slightly behind recent changes, and Rollmate checks again shortly after. If it still looks out of date, open the Rollmate panel and select Update now.

Overdue counts or dates look out of date.

Time passing doesn’t trigger a change in Jira, so these are refreshed once a day. Use Refresh all values to update them now.

The banner says “Paused”.

Jira asked Rollmate to slow down. It continues automatically; you don’t need to do anything.

The Health tab shows failed updates.

Failed updates are retried automatically. If the count keeps growing, contact support with the error shown.

A field says it’s missing from Jira.

Its Jira field was deleted outside Rollmate. Choose Create it again on the Health tab.

The admin page says “Rollmate is paused”.

The site’s Rollmate subscription isn’t active. A Jira admin can renew it in Manage apps. See Pricing, and what happens if the subscription lapses.

I can’t open the Rollmate admin page.

You need Jira administrator permission to manage Rollmate.

Common questionsLink to this section

Does Rollmate use Jira Automation?

No. It doesn’t create or run Automation rules, so it doesn’t count against your Automation allowance.

Can Rollmate write into my existing Story points field?

No. Rollmate writes only to its own read-only fields, so people and other tools can’t overwrite the values. If you keep a total in another field today, use Compare with another field to check the two against each other.

Can people edit a roll-up value by hand?

No. The fields are read-only, so the value always matches the children.

Does any data leave Atlassian?

No. Rollmate runs on Atlassian Forge with no outside servers. See Data and security.

Will people see children they don’t have access to?

The Rollmate panel reads work items as the person viewing it, so its breakdown only shows children they can see. The field value itself is the total across all children, like any field calculated by an app.

Does it work with sub-tasks and levels above epics?

Yes. Choose Every level below to count sub-tasks of stories under an epic. A field works on any work item that has children, not only epics.

Does it work in team-managed projects?

Yes, the values are calculated the same way. Add the field to the work item layout yourself, as described in Show the fields on work items.

Why is my field empty instead of 0?

If no child has a value for the field it reads, Rollmate leaves the field empty. That way “nothing to add up” looks different from “adds up to zero”.

Still stuck?

Email support@valeframe.com.au or see the support page.